- Start Date: November 1ST 2023
- End Date: May 31st 2024
- Duration: 7 Months
- Donar: Stabilization fund through IOM
- Project Budget KES 9,911,160
- Project Location: Wajir East and Wajir West
- 926 households were targeted for 3 months
- Wajir West 726
- Wajir East 200
- Paid Kes 8,440 per month
- Cash transferred (WW 18,382,320, WE 5,064,000) 23,446,320